Background
Unipod is an expanded polystyrene (EPS) manufacturing and recycling company that supplies waffle pods to residential builds across Victoria.
Before you begin
- Ensure you have access to Scheduler. If you don't see Scheduler in your available Elda (Chrome) shortcuts, you may need to request access to it.
- Please see our article on how to Request access to an Elda Application.
Steps to follow
- Once the job has been factoried for the correct delivery date and the status shows tags assigned, in the job schedules list highlight the schedule by double clicking the line.
-
Right click and select EDI TRANSFER and select Vendor UNIPOD
- Once the items have been ticked you can click the button on the bottom left hand side “Create PO from Selected”.
- Make sure to change the dates as per booking request.
- If the waste collection date has also been provided this can be updatated with a waste delivery status of Firm Delivery Date. If no date for waste collection provided tick “Confirm Same Waste Pick Up Date” and change “Waste Delivery Status” to “ To be Advised”.
- Delivery comments are added to the EDI by ticking the Copy from Schedule box. This will ensure the delivery instructions are the same for both steel & pod deliveries.
- Ensure the freight charge is correct and once happy click COMMIT.